Port facilities DWG · MB-123
Port facilities · Reconstruction
Odesa, reconstruction of Berth No. 29 at Odesa Sea Commercial Port
Reconstruction of Berth No. 29: a 256 m long quay, backland crane track, dredging down to 13.5 m depth.
Designed by GT Project Ukraine SE.
Scope of works:
construction of a 256 m quay;
backland crane track on piled foundations;
foundation for a 35 m lighting mast;
dredging works to 13.5 m depth.
Structure: anchored bulkhead of 1420×14 mm steel tubular piles with a PU-32 steel sheet-pile front screen and a reinforced-concrete pile cap. The berth meets Category "0" loading and is equipped with fenders, mooring fittings and lighting.
Start: March 2001. Completion: September 2002.
Gallery
2Location
46° 29.297′ N · 30° 44.910′ E